When you buy off-plan, you do not pay everything at signing : the price is paid in instalments, as the works progress. The law caps the sums that can be requested from you at each stage.
The schedule set by law
Article R. 261-14 of the French Construction and Housing Code sets cumulative ceilings :
| Construction stage | Maximum cumulative amount |
|---|---|
| Foundations completed | 35% of the price |
| Weathertight (roof on) | 70% of the price |
| Building completed | 95% of the price |
| Handover of the keys | 100% |
Between these stages, the developer may schedule intermediate calls (walls up, windows in, partitions…), without ever exceeding these ceilings. Each call for funds comes with a progress certificate issued by the project manager.
An example schedule
| Stage | Cumulative | Call on €250,000 |
|---|---|---|
| Foundations completed | 35% | €87,500 |
| First-floor slab | 45% | €25,000 |
| Watertight | 70% | €62,500 |
| Windows in (airtight) | 80% | €25,000 |
| Partitions completed | 85% | €12,500 |
| Building completed | 95% | €25,000 |
| Handover | 100% | €12,500 |
And your loan?
Your bank releases the funds as the calls come in, on presentation of each call for funds. During construction, you only pay interest on the sums released : this is interim interest. Many banks offer a repayment deferral : you only start repaying the capital at handover, which avoids paying rent and a full monthly instalment at the same time. That is why the maximum loan term is extended to 27 years for new homes when a deferral is planned.
The balance on handover
The remaining 5% is paid when the keys are handed over. If you disagree about whether the home complies with the contract, this balance can be placed in escrow (deposited with a third party) until the problem is resolved. See our page on handover and snags.